Updated to show the progress. Passed final inspection with the county yesterday. Concrete should be here Mon or Tues next week. As soon as it sets the garage door guy will install the overhead doors and the electrician will do his thing...I'm guessing towards the end of next week. Once that's done I need to install a security door (I doubt that's necessary but I'm gonna do it anyway), paint the man door and move my stuff in.
End of Week 2:
Monday- Framed and starting on the metal trim.
Tuesday- Windows and man-door framed and installed. Wall insulation and steel siding on three walls.
Wednesday- Roof insulation and metal installed over the garage portion.
Thursday- Roof, steel and trim completed.
Friday- Gravel delivered, spread to depth and compacted inside garage, awaiting concrete on Monday. Parking area restored with gravel. Also, the all-important antique copper weather vane that's followed us from home to home for decades, sits proudly in it's new place.